NEW INFORMATION:
Attached is the County’s plan review comments.
Please show “HP1” – condenser @ 585 lb. and forward us an updated S4 drawing.
Use the following project revision in title block:
2 2-23-21 County Comments
Conversion of existing 2745 sq ft space.
Please add allowance for parking.
Please send us price for possible NIGHT WORK involved.
DEMO: PAGE A5 REMOVE EXISTING STADING SEAM ROOF FROM EXTEREIOR PITCH ROOF WALLS TO INSTALL NEW BRICK VENEER, REMOVE EXISTIBNG WINDOW, REMOVE EXISTING STUCCO FINISH AND REMOVE EXISTING STORE FRONT PARTIALLY. REMOVE EXISTING DOOR PAGE A1, REMOVE EXISTING EISTING PARTITION AND RAMP,
STORE FRONT: PAGE A1 EXISTING DOOR TO BE REMOVED AND INSTALL NEW STORE FRONT ASSEMBLY, NEW WINDOW HEAD AND NEW WINDOW SILL, NEW ORANGE DOORS PAGE A5,
STEEL: PAGE A1 NEW HAND RAIL 1 ½” , NEW STEEL LINTEK #4, PAGE S-1, S-2 NEW STEEL BEAM AT OPENINGS AND NEW W8X18 STEEL BEAM POCKET WITHIN MASONRY. THERE IS A MASONRY WORK IS INVOLVED FOR THE OPENINGS AND PATCHING. BEAM TO BEAM CONNECTIONS DETAIL S-3,
DRYWALL/METAL FRAMING/CEILING/BLOCKING: PROVIDE TWO LAYERS OF 5/8” DRYWALL TENANT SIDE PAGE A1, PROVIDE ONE LAYER OF ½” DRYWALL PAGE A1, , PARTITION BY DÉCOR BY PROVIDE ALTERNATE PRICE, ALL INTERIOR WALLS TO BE 25 GA METAL STUDS AND ALL WOOD FRAMING UP TO FLOOR DECK AND TOP PLATE TO BE PT, S-1 F/I NEW MARINOWARE 6CW18 JOISTS , SEE ALL S DRAWINGS, NEW LANDING FRAMING, INSTALL TWO(20 PT SILL CENTERED ABOVE BEARING LINE, NEW LANDING FRAMING, NEW STEP, NEW ¾” T&G SUBFLOOR , SEE PAGE S-3 FOR NEW FLOOR FRAMING, SHEATING PAGE S-2, PAGE A1 BUILD UP LANDING WITH 2X10, NEW 42” HIGH WALL PAGE A1, RAMP AND STEPS, PROVIDE PLYWOOD PER PAGE A1 ON THE WALLS AND WHERE THE SHELVES GOES, F/I DURACK PAGE A1 # 2 WHERE TILES AND KITCHEN WALLS ARE, ALL WOOD TOUCHING BLOCK SHALL BE PT LUMBER PAGE A1 #3, SEE PAGE A4 FOR FIRE RATED SHAFT,
EXTERIOR WORK/TRESPA PURA NFC PAGE A5 : PAGE A1 PROVIDE ½” EXTERIOR PLYWOOD #1, SEE PAGE , SEE PAGE A5 FORBTRESPA PURA EXTERIOR PANELS APPROX 700 SQ.FT. + 460 SQ.FT.
CMU: PAGE A1 INFILL EXISTING OPENING TO MATCH, PATCH AND NEW WORK FOR STEEL CONSTRUCTION,
ROUGH CARPENTRY: PAGE S-4 NEW 1 3/4:”X51/4” MICRO LAM LVL, 2X6 HEADERS, 2X12 TO EXISTING RAFTERS,
KNOX BOX: PAGE A1,
DOORS/HARDWARE: PAGE A6 NEW REAR DOOR
RESTROOM ACCESSORIES:
FIRE SPRINKLER:
FIRE ALARM: PAGE F1.1
FIRE EXTINQUSHERS: PAGE A1,
ANSUL SYSTEM: BY OWNER
ELECTRIC: PAGE A1 EXISTING TEMP PANELS TO BE REMOVED OR RELOCATED,
PLUMBING:
HVAC:
FIRE EXTINGUSHERS: PAGE A1 #14
SS/FRP: PLEASE SEE PAGE A1 NOTES FOR ALL SS WORK, F/I SS CAP THAT RUNS ENTIRE LENGTH OF BULKGHEAD, 13 PCS OUTSIDE CORNERS AND CAPS #5, SS PANEL BEHIND THE OVENS #2, SS CEILING PANELS SEE PAGE A1, A3 TWENTY-EIGHT (28) PCS., PAGE A1 SS CAP UNDER THE BULKHEAD, SS CEILING PANELS 21 PCS., SEE PAGE A13 SS PANEL IN THE KITCHEN FURNISHED BY KES, INSTALLED BY GC.
ROUGH CARPENTERY: BUILT UP WOOD LANDING 2X10 W/FFLOOR JOISTS PAGE A1, APPROX 5’X5’ , ROOF FRAMING PAGE A4 TO REINFORCE RTUS, RAISED FLOOR PAGE A4A PLS ALSO PRICE TO POCKET INTO EXISTING FOUNDATION WALLS , PAGE A6 PROVIDE ½” PLYWOOD SHEATING W/WATER BARRIER AFTER REMOVING STANDING SEAM ROOF,
FIRE STOPPING :
TILE: F/I CEMENT BOARDS OVER NEW/EXISTING PLYWOOD FLOORING, WATER PRROFING SEE PAGE A2 LATICRETE 9235 VERY LARGE AREA,
SLIP RESISTENT FLOORING OVER RAMPS: PAGE A2 WOOSTER PRODUCTS 500-NG OR EQUAL,
SISTENT STUDDED FLOORING: PAGE A2
DÉCOR/FURNITURE PACKAGE:
WALK IN COOLER/FREEZER: SEE PAGE A4 FOR CONDENSORS, OWNER SUPPLIES ITEK INSTALLS.
PAINT: SEE PAGE A5 PAINT ROOF COPINGS, PAINT EXTERIOR BAND WHITE, PAINT EXISTING CANOPY RED, PAIN THING BRICK PAGE A5,
THIN BRICK: PAGE A5/A6 WHAT DO WE INSTALL OVER WOOD EXTERIOR FINISH AFTER WE REMOVE THE STANDING SEAM ??
NEW NICHIHA PANELS: PAGE A5,
DÉCOR PACKAGE:
KITCHEN EQUIPMENT:
ROOF:
NEW WINDOWS: PAGE A5 AND PAGE 6 PAGE A5 NINE (9) NEW SLIDER WINDOWS,
File ID | File Name | Link |
3594 | Popeyes – Silver Springs, MD ARCH 2020-10-02 | DOWNLOAD |
3595 | Popeye's – Silver Springs, MD Mech For Information Only 2020-10-27 | DOWNLOAD |
3596 | Popeye's – Silver Springs, MD MEP 202-10-02 | DOWNLOAD |
3644 | A5-REV-5_12-3-20 | DOWNLOAD |
3597 | 1- New Partial Plans 10-29-2020 Popeyes Silver Spring, MD | DOWNLOAD |
3598 | For Subs 1- Draft-G20-14-letter-1 | DOWNLOAD |
3603 | 04481589 – Proposed Popeye's ACM Survey Silver Spring MD | DOWNLOAD |
3723 | 1-Full Set- Revised Popeyes Silver Spring, MD | DOWNLOAD |
3724 | CertificationOfModifiedDrawings-Arch | DOWNLOAD |
3725 | CertificationOfModifiedDrawings-MEP | DOWNLOAD |
3726 | G20-14-letter-1 | DOWNLOAD |
3727 | G20-14-letter-2 | DOWNLOAD |
3728 | MEP Response Narrative 2021-02-18 | DOWNLOAD |
3731 | 1-Full Set- Revised Popeyes Silver Spring, MD | DOWNLOAD |
3732 | POEYES SILVER SPRING SCOPE OF WORK | DOWNLOAD |
3746 | M0.2 SPECIFICATIONS | DOWNLOAD |
3747 | M1.2 ROOF PLAN | DOWNLOAD |
3750 | Construction Set-Popeyes Silver Spring, MD 3-8-2021 | DOWNLOAD |
3751 | G20-14-letter-3 for subs | DOWNLOAD |
3752 | MEP Response Mech and Elect Narrative 2021-03-08 | DOWNLOAD |
3753 | MEP Response to Plumbing Narrative 2021-03-08 | DOWNLOAD |
3765 | Montgomery County 2018 Energy Code Analysis Checklist Popeyes Silver Spring, MD 3-25-2021 | DOWNLOAD |
3766 | Popeye’s Silver Spring, MD – Mechanical and Electrical Response Narrative Popeyes Silver Spring, MD 3-25-2021 | DOWNLOAD |
3767 | 1- Full Construction Set- Popeyes Silver Spring, MD 3-25-2021 | DOWNLOAD |
3891 | Popeye’s – Silver Springs Plumbing 2021-04-13 | DOWNLOAD |
3892 | 1- Full Construction Set- Popeyes Silver Spring, MD 4-13-2021 | DOWNLOAD |
4201 | 1- Full Set Construction Plans- Popeyes Silver Spring, MD 7-9-2021 | DOWNLOAD |